Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 96.305 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) | All types of Soils | 9,96,983 | Cum |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) | Embankment with suitable materials deposited at site from roadway and drainage excavation | ||
From roadway excavation | 10,19,841 | Cum | |
From Borrow Area | 16,389 | Cum | |
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. CULVERTS | ||
EW | a) In all types of Soils by mechanical means | 8,513 | Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 632 | Cum |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M30 | 6,385 | Cum |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 430 | MT |
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. BRIDGES | ||
EW | a) In all types of Soils by mechanical means | 5,922 | Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 609 | Cum |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M30 | 3,661 | Cum |
RCC M35 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 | 1,732 | Cum |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 577 | MT |
Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 96.305 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) All types of Soils | 9,34,545 | Cu m | |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) Embankment with suitable materials deposited at site from roadway and drainage excavation
|
Cu m | ||
From roadway excavation | 9,64,263 | Cu m | |
From Borrow Area | Cu m | ||
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. | ||
EW | a) In all types of Soils by mechanical means | 7,011 | Cu m |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 558 | Cu m |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M15 | 4,897 | Cu m |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD barreinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 306 | MT |
4 |
Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. BRIDGES
|
||
EW | a) In all types of Soils by mechanical means |
5,922 |
Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 539 | Cum |
RCC M30 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
2,476 | Cum |
RCC M35 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
1,510 | Cum |
STEEL MT |
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600. | 484 | MT |
Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 96.305 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) All types of Soils | 9,34,545 | Cu m | |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) Embankment with suitable materials deposited at site from roadway and drainage excavation
|
Cu m | ||
From roadway excavation | 9,64,263 | Cu m | |
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. | ||
EW | a) In all types of Soils by mechanical means | 7,011 | Cu m |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 558 | Cu m |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M15 | 4,897 | Cu m |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD barreinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 306 | MT |
4 |
Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. BRIDGES
|
||
EW | a) In all types of Soils by mechanical means |
5,922 |
Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 539 | Cum |
RCC M30 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
2,476 | Cum |
RCC M35 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
1,510 | Cum |
STEEL MT |
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600. | 484 | MT |
Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 95.755 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) All types of Soils | 5,56,615 | Cu m | |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) Embankment with suitable materials deposited at site from roadway and drainage excavation
|
Cu m | ||
From roadway excavation | 5,33,480 | Cu m | |
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. | ||
EW | a) In all types of Soils by mechanical means | 3,783 | Cu m |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 273 | Cu m |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M15 | 278 | Cu m |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD barreinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 168 | MT |
4 |
Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. BRIDGES
|
||
EW | a) In all types of Soils by mechanical means |
4,027 |
Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 191 | Cum |
RCC M30 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
361 | Cum |
RCC M35 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
913 | Cum |
STEEL MT |
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600. | 169 | MT |
Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 95.755 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) All types of Soils | 3,40,497 | Cu m | |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) Embankment with suitable materials deposited at site from roadway and drainage excavation
|
Cu m | ||
From roadway excavation | 3,19,387 | Cu m | |
From Borrow Area | Cu m | ||
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. | ||
EW | a) In all types of Soils by mechanical means | 3,038 | Cu m |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 140 | Cu m |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M30 | 198 | Cu m |
STEEL MT | Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 45 | MT |
4 |
Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. BRIDGES
|
||
EW | a) In all types of Soils by mechanical means |
1,716 |
Cum |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 57 | Cum |
4 |
Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. UNDERPASSES
|
||
EW | a) In all types of Soils by mechanical means |
1,832 |
Cum |
PCC M15 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 |
46 | Cum |
RCC M30 |
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M35 |
167 | Cum |
STEEL MT |
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 17 | MT |
Sr. No | Description | Qty | Unit |
---|---|---|---|
1 | Clearing and grubbing for road land complete as per Technical Specification Clause 201 | 93,655 | Hect |
2 | Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads. | ||
a) All types of Soils | 1,24,125 | Cu m | |
3 | Construction of embankment complete as per technical specification clause 305 with all leads and lifts. | ||
b) Embankment with suitable materials deposited at site from roadway and drainage excavation
|
Cu m | ||
From roadway excavation | 1,15,689 | Cu m | |
4 | Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads. | ||
EW | a) In all types of Soils by mechanical means | 1,253 | Cu m |
PCC M15 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M15 | 72 | Cu m |
RCC M30 | Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M15 | 62 | Cu m |
STEEL MT |
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 1600 | 35 | MT |