Welcome To PKG-2

Development of Six Lane access controlled Greenfield Highway From Vanavolu to Vankarakunta of [NH-544G] Bengarulu-Vijayawada Economic corridor on HAM Mode under Bharatmala Pariyojana Phase-I in the State of Andhra Pradesh (Package-2).

  • 29-8-2024

    Project Milestone 1

    200 Days (From Appointed Date)
    20% progress

  • 20-3-2025

    Project Milestone 2

    450 Days (From Appointed Date)
    35% progress

  • 18-9-2025

    Project Milestone 3

    600 Days (From Appointed Date)
    75% progress

  • 1-3-2026

    Schedule Completion Date

    910 Days (From Appointed Date)
    100% progress

Our Latest Gallery

461.23 Cr

Bid Project Cost

6 Lane

No. Of Lanes

730 Days

Construction Period

2

Toll Plaza

GET IN TOUCH
premium bootstrap themes

Let's get in touch

We're open to any suggestion or just to have a chat.

020 2563 6060
Raj Path Infracon Pvt. Ltd. Amar Business Zone, C-Wing Office nos. 1302,3 & 4 Veerbhadra Nagar Baner, Pune 411045

All fields are mandatory

Thank You! We will get back to you soon.